Guide to Surviving the Construction Process

31Bs11yRlML
Ted Bumgardner

“Better to be wise by the misfortunes of others than by your own.”   Aesop

Getting an education in the intricacies of managing a complex construction project can be a very expensive process, especially when those lessons come from living through the challenges of looking out for your own money.   The process of building your dream home can be very creative, exciting and fulfilling, or it can also seem like a never ending nightmare that bleeds you dry both emotionally and financially.  The difference between a good and a bad experience come down to two things:

  1. How well prepared you are for the journey.
  2. How resilient you are when things change.

My mission in this article is to help you prepare for the journey.   Even in the best planned projects, changes and surprises will occur.  Whether it’s the weather, the contractors, the building department, or any of a zillion things that can create a situation where the plan must change, one thing is certain; things will change.  Some people deal well with change and find opportunities in the dynamics of the situation.  For some, however, the construction process with all its uncertainties only leads to disappointment and frustration.  The construction game is best played by those who have a clear vision of what they want and at the same time an open mind for the possibilities that will emerge.

Lesson 1:  Do business with the right people.  This is perhaps the single most important  thing that you can do to obtain the best outcome.  Spend the time it takes to check references on those you do business with.   The architect is a good source for good contractors, but don’t just take the architect’s recommendation and stop there.  There is a much greater chance of the architect and contractor doing future business together than the chance of either of them working with you again.  Know that there is a culture in residential construction of the contractor and architect looking out for each other to the owner’s detriment.  This can go all the way from there actually being a “finder’s fee” paid to the architect by the contractor to an arrangement between the architect and contractor where the contractor will not charge you for correcting the architect’s screw ups in exchange for the architect recommending the contractors billings for payment.  In either event, they are helping themselves to your money.  

I suggest that you develop a list of three prospective contractors.  Request from each of them an outline of their qualifications and references.  Interview them with a committee made up of you, your architect, and a friend who you respect who hopefully has been through the process themselves or is in the construction business.  Check their contractor’s license status by going to www.cslb.ca.gov  .

Lesson 2: Bid or Negotiate? Most of the best custom home contractors will not participate in a simple bid project.  They don’t have to since they typically have enough business without bidding.  You can, however, still get the benefit of the buy and get a very competitive cost of construction by “bidding a negotiated contract”.  Here is how it works:

  • First, understand that we are setting out to enter into a negotiated Guaranteed Maximum Price (GMP) contract.  This is a commonly used delivery method for private work where you can engage the contractor early in the design process and pay them for the cost of construction plus a fee for their services.  The AIA has a good contract to use for this called their AIA A101 2007.
  • Have the contractors  you have interviewed and that you believe would be good to work with from the process in Lesson 1 give you a quote on:
    • The fee they would charge on top of cost
    • The time of construction based on the conceptual plans
    • The mark up on change order work
    • The rates they would charge for any of their self performed labor
    •  And the cost they would charge for “General Conditions”, the cost of project supervision and all temporary facilities, temporary toilets, fences, etc.
  • Be sure  you stipulate that you intend to use the AIA A201, 2007 and that you expect them to obtain at least 3 quotes on all of the major subcontract trades.

There are many construction delivery methods which can be used, and many variations and strategies.  Never enter into an open ended “cost plus” arrangement without a Guaranteed Maximum Price or a well defined process to get to one.  

Lesson 3: Negotiate the right contract terms. The process of constructing a home is a virtual orchestra of diverse talents, working together for the first time, to create something that is unique and has never been assembled in this form before.  They are all looking out for their own interests first and they all want your money.  They all have the objective of getting considerably more of your money than what it will cost each of them to produce their contribution to your project.  In some periods of time, there are more contractors than there are construction projects.  In some periods, there are more projects than there are contractors.  Your ability to get the most for your money is a function of which period of time you are buying in and how well you negotiate the deal. 

There is an old saying in construction contracting, “The owner gets to play offense until they sign the contract, after that they only get to play defense.”   So make sure you have left yourself in the best position possible when you sign the contract.

Some tips on contracts with your contractor:

  • Never do an open ended “cost plus” agreement.   If the total scope and cost are undetermined, then contract in phases for work that can be determined.  If you must go “cost plus”, be sure you have defined what is project cost and what is covered in the contractor’s fee.  Also nail down the rates that will be charged for any labor and the process that the contractor will use for obtaining subcontractor quotes and material purchases.  
  • Never simply default to the contractor’s form agreement.  It is written to protect him, not you.  There are many very good industry standard agreements out there that you can review and learn from.  The American Institute of Architects (AIA) has developed perhaps the most commonly uses form agreements in the industry.  
  • Have the contractor indemnify you, hold you harmless, and defend you from all losses arising out of his work.  If you don’t know what this means, consult your attorney or read up on the subject.  When something goes wrong at the project, someone gets hurt, or there is a serious defect with the construction later, this clause and the insurance provisions may be the most important paragraphs in the contract.
  • Be sure the contractor has good general liability insurance and make sure you are named as an additional insured under his policy.  You should also make sure that the General Contractor requires all of his subcontractors to have proper insurance and that all of them name you as an additional insured as well.  Have your insurance agent review the general contractor’s insurance coverage. 
  • Be sure you have a property loss policy on the construction project.  This is referred to in the industry as a “Builder’s Risk” policy.  I recommend that this coverage is purchased by the owner and not the contractor.  This policy will cover the project for property loss such as fire while under construction and should be discussed with  your insurance agent.
  • Be sure you stipulate a project completion time and liquidated damages in the event that the project takes longer to build than anticipated.  Stipulated liquidated damages are a set cost per day that should reflect your cost should the home not completed per the contract completion date.  These costs usually include things like the costs for alternative living arrangements, interest charges for the construction loan and property taxes.  
  • Look carefully at the termination language and have an open discussion with the contractor regarding what happens if this deal doesn’t work out or if you decide to terminate before construction starts or if the contractor or you gets hit by a bus, etc.  I know it is honeymoon time and everyone is looking at the world through rose-colored glasses, but contracts are much easier to get into than to get out of.
  • Never pay a big upfront deposit or other upfront payment to a contractor, never!  The California Contractors License Board (CSLB) limits upfront payments to a contractor to 10% of the contract or $1,000, whichever is less.

Lesson 4: Payments to the Contractor. 

Contractors, subcontractors, and material suppliers who perform work or send materials to your project have lien rights to your property.  Basically, if you pay your general contractor and that general contractor fails to pay his subs and suppliers, those subs and suppliers can lien your property and you may have to pay them directly to remove the lien – even if you have already paid the money for the work to the general contractor.  There are basically two ways to avoid this risk:

  1. Require that your General Contractor provide a Payment and Performance bond.  This is a bond that you will have to pay for that protects you from failures of the contractor to perform the work or failures of the contractor to pay his subs and suppliers.  This is a fairly expensive way to go and will cost somewhere in the neighborhood of 2% of the contract price.  The cost goes down based on the financial strength of the contractor and the contractors bonding history.  Even if you don’t intend to require a bond, it may be a good idea to ask your perspective contractor to tell you their bonding rate – the rate is very telling in itself.  Many residential contractors do not have a history of bonding, so they may not be able to bond the project.

 

  1. Fund Control is another alternative to protect you from a contractor’s failure to pay his subs and suppliers.  This is a service where a company, like Dixieline Fund Control, will disburse payment vouchers to contractors upon your approval of the work.  The fund control company will collect the proper lien waivers from the contractors and help to protect you from liens against your property.  Fund Control is much less expensive than a bond and is typically required by construction lenders.

The contractor has a right to require some form of assurance that you are able to pay for the construction.  The fund control process is also a good way to provide that assurance.  The fund control will require that funds are secure in an amount to cover the contract for construction and will provide a process for line item budget management for the project.

Lesson 5: Change Orders.  One thing is certain, things will change.  The contract provides for a cost and time for construction based on the construction documents, the plans, etc.  Changes will occur primarily due to:

  • Errors and omissions in the plans
  • Unforeseen conditions
  • Regulatory Agency Directives
  • Owner Elective Decisions

Basically, the contractor is responsible to have made a reasonable anticipation of the requirements of the project.  When things occur beyond reasonable anticipation, the contractor is entitled to receive a reasonable adjustment in contract price and time.  The work will cost quite a lot more when it occurs due to a changed condition compared to what the same work would cost when it is purchased as a part of the base contract.  Project studies have shown that the premium for change order work will be around 40% or more over base contract work due to the inefficiencies in buying and administering change order work.  The volume of change order work can be mitigated by:

  • Allowing ample time for the development of the plans, reviewing the plans, having a peer review of the plans.
  • Making sure there has been ample due diligence in soils investigations and research into past construction on the site to minimize unforeseen subsurface conditions.
  • Spend time with the architect looking at the plans to make sure that you and the architect have the same vision, get the architect to help you visualize each room, study the orientation of the structure on the site for view corridors, etc.

When changes do occur, follow the process outlined in the contract for administration of the changes and make sure all changes are in writing!

Lesson 6: Administering the Process The AIA contract does a pretty good job of outlining the process for administering the construction contract.  Some architects are good at contract administration and some are almost worthless.  There are also “owner advocates” or owners representatives out there who can help to administer the process.  A few key concepts in contract administration can go a long way in keeping you out of trouble.

  • The AIA contract has an attachment (AIA A201) which is referred to as the General Conditions to the Contract for Construction sets forth how to deal with payment, change orders, etc., and if followed, will go a long way in keeping the project out of trouble.  
  • Have regular team meetings at the site with the contractor, the architect, and owner present.  Document the meeting with written meeting minutes that establish:
    • Each issue discussed
    • Who is responsible for what action
    • When the action due
  • At the end of every meeting, wrap up with a question to the contractor: “Other than what we have already discussed here today, is there anything that is holding you up or that you think will result in any additional cost to the project?”  Then document in the written meeting minutes the contractor’s response to that question.
  • The importance of the written meeting minutes cannot be overstated.  He who controls the meeting minutes controls the project and the meeting minutes are often the best written documentation for the project.  When a project goes into litigation, the reality established in the written documentation is the reality that counts.

Project issues are more like fish than fine wine; they don’t improve with age and only get stinkier as time goes on.  Deal with issues promptly and in writing to keep them from disrupting and dominating the project.   

Volumes have been written and careers have been spent exploring all of the strategic aspects of effective project management.  In this paper, I have tried to “dispense with the trivial many, in favor of the critical few” as it relates to staying out of trouble on your custom home project.  Most contractors will abhor the concept of written documentation as well as the concept of not only reading the contract provisions, but living by them as well!  I can tell you with certainty that if you follow the concepts that I have outlined here, your chances for a successful project and our chances of avoiding litigation will be greatly enhanced.

Related Articles

  • The Essential Place for Empathy in Construction Disputes 

    Several years ago, on a late evening flight to Dallas, we touched down in El Paso to drop off and take on passengers. The seat next to me had been left vacant by the deplaning passenger who sat next to me from San Diego, but was quickly filled by a clean cut young man in his late 20s with a white crew neck t-shirt, a brown leather bomber jacket, wire rimmed aviator glasses and hair cut “high and tight.”

    August 20, 2024
  • Sometimes “Time is Money” …but not always!

    The old adage that “Time is Money” has never been truer than as it relates to the development and construction of revenue producing properties. Between the Owner’s debt service expense on loans of tens of millions of dollars, lost revenue, and contractor’s time related costs, the cost per day can be tens of thousands of dollars.

    April 2, 2018

EXPERIENCE, YOUR BEST SOLUTION